Hi,
I have a query related to placement of replacement joint for Ground Position light(GPL) in the scheme plan(Not for Module 2, Signalling the layout).
If it is placed less than 5.5m from the GPL, is it required to have last wheel replacement facility or some form of facility to delay the replacement of signal.
I have seen a case where the replacement joint is placed less than 5meters from the signal(GPL), but there was no delayed replacement for that signal.
Can someone clear this query.
Many Thanks in advance.
P.S. Network rail standards says that the replacement joint should be around 5.5m to 20m from the signal(Main) but not clearly mentioned about the GPL.
I have a query related to placement of replacement joint for Ground Position light(GPL) in the scheme plan(Not for Module 2, Signalling the layout).
If it is placed less than 5.5m from the GPL, is it required to have last wheel replacement facility or some form of facility to delay the replacement of signal.
I have seen a case where the replacement joint is placed less than 5meters from the signal(GPL), but there was no delayed replacement for that signal.
Can someone clear this query.
Many Thanks in advance.
P.S. Network rail standards says that the replacement joint should be around 5.5m to 20m from the signal(Main) but not clearly mentioned about the GPL.