2012 Q7 Station layout options for turnback
#3
Thanks for your comments PJW.
Just thinking about all the scenarios that can cause degraded working to structure answers to similar questions, in my opinion these can be divided into two groups; broken train or broken infrastructure.
Within broken infrastructure there are several possibilities; broken rail, subsidence, landslide, tresspass all result in a line being blocked.
Points failure can lead to a loss of functionality (i.e. trains not being able to be routed to where they need to go).
Signalling failure due to loss of power or cable fault.