I was wondering if anyone could advise on the timing for operation for MCB-OD in the UK. From x21 it states the timing sequence takes 35s from the start of the amber. Later on it goes on to say 35 + 10(what is the 10s for?)this 45 plus 20s for MROT for 2nd train. Is there a strike in point at 65s for 2 lines then with 20s delay timer started then? And at what point does the sequence start after the 20s timer or is it another 10s after this?
Also does the OD scan continuously after its warmed up until it's last scan before the crossing clear is given for the protecting signal to show a proceed
Any advice would be appreciated.
Thanks
Also does the OD scan continuously after its warmed up until it's last scan before the crossing clear is given for the protecting signal to show a proceed
Any advice would be appreciated.
Thanks